Preparation of design documentation for the reconstruction of the Okučani – Vinkovci railway section

 

Section Okučani – Vinkovci (131.0 km) is an integral part of the main corridor railway line for international traffic M104 Novska – Tovarnik – state border – (Šid) on the corridor RH1, and in the European framework it is an integral part of the Core Trans-European Transport Network – TEN-T.

On 27 October 2017 HŽ Infrastruktura d.o.o. signed the Grant Agreement INEA/CEF/TRAN/M2016/1365734 as part of the Connecting Europe Facility Transport Sector (CEF – Connecting European Facility) with the European Climate, Infrastructure and Environment Executive Agency (CINEA). The value of the Grant Agreement is EUR 11.2 million, of which EUR 9.5 million, or 85 percent is co-financed from CEF and the remaining amount of EUR 1.7 million, or 15 percent, is co-financed from own funds.

The signed Grant Agreement covers the following activities:

  1. Project management, publicity and visibility
  2. Study of the modernization of the railway line on section Okučani – Vinkovci, which includes Conceptual Design, Feasibility Study, Cost-Benefit Analysis, and Environmental Impact Assessment
  3. Preliminary Design with obtaining a Location Permit
  4. Main Design with obtaining construction permits
  5. Settlement of property rights
  6. Technical part of procurement documentation for works

On 17 May 2019 HŽ Infrastruktura signed Contract for preparation of study documentation with a consortium consisting of GRANOVA d.o.o., ŽPD d.d., INSTITUT IGH d.d., RIJEKAPROJEKT d.o.o. and IPZ d.d. in the amount of EUR 1.4 million. The Contract for preparation of study documentation was completed in May 2022, and the following documentation was prepared: Conceptual Design and Multi-Criteria Analysis, Feasibility Study, Cost-Benefit Analysis and Environmental Impact Assessment.

HŽ Infrastruktura signed Contracts for preparation of project documentation for civil engineering and electrical power subsystem:

– on 2 August 2022 for subsection I Okučani (excluded) – Nova Kapela/Batrina (included) with the company TRAMES d.o.o. in the amount of EUR 1.0 million

– on 11 February 2022 for subsection II Nova Kapela/Batrina (excluded) – Slavonski Brod (included) HŽ Infrastruktura with a consortium consisting of ŽPD d.d., IPZ d.d., GRANOVA d.o.o., INSTITUT IGH d.d., RIJEKAPROJEKT d.o.o. and DALEKOVOD-PROJEKT d.o.o. in the amount of EUR 1.1 million

– on 1 August 2022 for subsection III Slavonski Brod (excluded) – Strizivojna/Vrpolje (included) with a consortium consisting of ŽPD d.d., IPZ d.d., GRANOVA d.o.o., INSTITUT IGH d.d., RIJEKAPROJPEKT d.o.o. and DALEKOVOD-PROJEKT d.o.o. in the amount of EUR 1.3 million

– on 17 March 2022 for subsection IV Strizivojna/Vrpolje (excluded) – Vinkovci (included) with the company CONSULTANTS d.o.o. in the amount of EUR 0.7 million.

All contracts include the preparation of:

  1. Preliminary Design with obtaining a Location Permit
  2. Main Design with obtaining building permits
  3. Settlement of property rights
  4. Technical part of procurement documentation for works

On 19 January 2023 HŽ Infrastruktura signed the Contract for preparation of project documentation for traffic-control and signalling and interlocking subsystem with a consortium consisting of ZAGREB SIGNAL d.o.o., ŽPD d.o.o., GRANOVA d.o.o., MA3X SAVJETOVANJE d.o.o. in the amount of EUR 1.5 million.

The contract includes the preparation of:

  1. Main designs
  2. Technical part of procurement documentation for works

For more information about the project please contact korporativne.komunikacije@hzinfra.hr.

Skip to content